The 28-Day Notice in FIDIC: What the Courts Now Say

The time bar in the 1999 and 2017 forms, the 2026 Privy Council ruling, and where Egyptian law stands

November 20269 min read

On large construction projects in Egypt, the contract is often written on a FIDIC form. Those forms hold a short deadline that decides the fate of claims more than any other clause: 28 days to send a Notice of Claim. The decisions of the last three years have applied it more strictly than many contractors expect. This article sets out what the contract says in both editions, what courts and tribunals have held up to 2026, and where Egyptian law stands.

What the Contract Says, in Both Editions

The rule is the same in both editions. The Contractor must give notice of the event as soon as practicable, and no later than 28 days after it became aware, or should have become aware, of it. If it does not, there is no extension of time, no additional payment, and the Employer is discharged from liability for the event. The differences lie in what follows the notice.1

1999 Editions2017 Editions
Clause20.120.2
NoticeWithin 28 days of when the Contractor became aware, or should have.The same period (20.2.1). It must be a “Notice” as defined: in writing, identified as a Notice, and sent under clause 1.3.
If it is lateNo time, no money, and the Employer is discharged.The same. The time bar now applies to the Employer's claims too.
The Engineer's first replyNone.14 days to say, with reasons, that the Notice is late (20.2.2). If the Engineer is silent, the Notice is deemed valid.
Detailed claimWithin 42 days of awareness.Within 84 days of awareness (20.2.4).
If the detailed claim is lateNot a bar. The award takes account of any prejudice to investigating the claim.If the statement of the contractual or legal basis is missing, the Notice is deemed to have lapsed, and the Engineer must say so within 14 days.
Can lateness be excused?No provision.Yes, within clause 20.2.5: prejudice to the other Party, and its prior knowledge of the event or of the basis of the claim.
DecisionThe Engineer responds within 42 days.Clause 3.7: 42 days to agree, then 42 days to determine. Then a Notice of Dissatisfaction within 28 days.

Notice the words “should have become aware”. The clock does not only start on the day you actually found out; it starts on the day a careful contractor would have known.

The 2022 Reprint

FIDIC reprinted the 2017 editions with amendments published in November 2022 and effective from 1 January 2023. Three of them bear on claims. First, the definition of “Claim” no longer covers matters to be agreed or determined under clause 3.7(a). Second, there is a new definition of “Dispute”, which now needs three things: a Claim or a 3.7(a) matter; its rejection in whole or in part by a determination or a deemed rejection; and a Notice of Dissatisfaction. Third, FIDIC's guidance now says in terms that the 84 days in clause 20.2.4 run from awareness of the event, not from the date of the Notice.2

If your contract is on a 2017 form, ask first which printing it is. The two definitions change when a Dispute exists, and when the dispute board's time limits start.

What the Courts Now Say

Obrascon, England, 2014

In Obrascon Huarte Lain v Attorney General for Gibraltar, the Technology and Construction Court said notice may be given before the delay occurs or once it starts, and that the clause is not to be construed strictly against the Contractor. No particular form is required, but the notice must be in writing, describe the event, and be recognisable as a claim. A progress report saying that rain had “affected the works” was not enough.3

Panther, DIFC Courts, 2023

In Panther Real Estate v Modern Executive Systems, the Court of Appeal held on 12 May 2023 that the 28-day notice is a condition precedent, and that time runs from awareness of the event itself, not from awareness of its effect on progress; on that point it declined to follow Obrascon. It rejected a good-faith argument for getting around the bar. On the first-instance findings, the Employer had been responsible for 306 of 325 days of delay. The 42-day period for the detailed claim, by contrast, is not a condition precedent.45

FIVE v Reem, DIFC Courts, 2023

The other side of the coin: notices on time, detailed claims years late. The claim survived, because the lateness of the detail had not prejudiced the other side. As reported, the contractor there had sent 212 notices in the course of the project.6

Uniform Building Contractors v WASA, Privy Council, January 2026

The most recent decision, and the most senior. On an appeal from Trinidad and Tobago under the 1999 Yellow Book, the Board said on 22 January 2026 that clause 20.1 is in classic condition precedent form, and that the 2017 form is more flexible but still a condition precedent. It added three points every contractor should know. Termination of the contract does not revive a claim that is already barred. Waiver of the time bar has to be pleaded and proved. And the Engineer has no power to waive it, because clause 3.1 stops the Engineer amending the Contract. Claim letters and invoices were not a proper claim.7

Chennai Metro, Madras High Court, 2025

As reported in Howard Kennedy's table of FIDIC cases, the court on 31 January 2025 set aside arbitral awards in the contractor's favour: a notice sent on 19 September 2014 about a change effective on 16 July 2014 was outside the 28 days, so there was no entitlement.8

In Civil-Law Systems

In 2017 the Polish Supreme Court treated the period as a contractual preclusive period the parties are free to agree, and did not apply to it the rule against altering limitation periods. That is the closest published analogue to the Egyptian debate over Article 388.9 Against that, the majority of an ICC tribunal in 2020 held that good faith stopped an employer recovering delay damages for delay it had itself caused, although the contractor had given no notices.10

Where Egyptian Law Stands

Article 388(1) of the Civil Code: «لا يجوز النزول عن التقادم قبل ثبوت الحق فيه، كما لا يجوز الاتفاق على أن يتم التقادم في مدة تختلف عن المدة التي عينها القانون»Prescription cannot be waived before the right arises, and the parties cannot agree a prescription period different from the one the law sets. Hence the well-known debate: is the 28-day bar a change to a prescription period, and so void, or an agreed deadline whose expiry forfeits a contractual entitlement, and so valid?

We found no published Court of Cassation ruling deciding the point for a FIDIC notice. A 2024 country note for the International Bar Association says the same: there is no clear court precedent, and the 2017 forms are little used.11 The view in the most recent comparative reference on construction arbitration in Egypt (2026) is that prescription periods are mandatory, but the parties may agree procedural time limits.12 A notice bar is treated as a condition precedent that binds the parties (Article 147); it can defeat the contractual remedy without touching the prescription period itself, and it remains subject to good faith (Article 148) and to the rule against abuse of right (Article 5).

One reported decision is worth reading. It is a CRCICA award (Case 281 of 2002, issued on 28 June 2004): the tribunal found the clause clear and the contractor in principle barred, but would temper that result by the parties' common intention and by good faith where the Employer or the Engineer plainly knew of the intention to claim.10

The practical conclusion: do not build your position on the debate. The published trend is that tribunals are more ready than courts to enforce the bar, and good faith is a narrow refuge that turns on the facts of each case. Did the Employer know of the event? Was it prejudiced by the delay? How late was the notice?

How Notices Fail

  • A paper that is not a Notice. A progress report, an updated programme and the minutes of a meeting are not notices. Under the 2017 forms, a document that does not identify itself as a Notice is not one.
  • Counting from the effect. After Panther, time may run from the instruction or the event, not from the day its effect shows on the critical path. Record the date you became aware of each event.
  • Relying on the Engineer. The Engineer's tacit approval, or silence, is not a waiver. Waiver needs unequivocal conduct by someone with authority to give it.
  • A missing legal basis. Under the 2017 forms, leaving out the statement of the contractual or legal basis within the 84 days makes the Notice lapse. A contractor can also be held to the basis it first stated.
  • Invoices and claim letters. They are not a claim in the sense the clause requires.

Employer Amendments in the Particular Conditions

Many employers shorten the 28 days or delete clause 20.2.5. FIDIC's Golden Principles (2019) require every time period to be of reasonable duration (Golden Principle 4), and give this as an example of a breach: requiring notice of a claim event within 5 days of awareness.13 The Principles are not legally binding, but they are an argument in negotiation, and in a good-faith case before a tribunal. Another common amendment requires the notice to name the clause it is given under.

How to Protect a Claim from Day One

  1. Keep a notice register on site, reviewed every week, listing every event that might lead to a claim and the date you became aware of it.
  2. When in doubt, send the notice. A few lines describing the event are enough; the figures follow.
  3. Follow the form: in writing, identified as a Notice, and sent by the means and to the address the contract names.
  4. State the contractual or legal basis in the detailed claim, and submit it on time.
  5. Keep contemporary records from the first day: minutes, dated photographs, correspondence.
  6. Read the Particular Conditions before you sign, and check which printing of the form you are on.

Why a General Model Gets This Wrong

FIDIC's forms are sold, not published free, so a general model did not learn clause 20.2 from its text. It learned from what has been written about it, and far more has been written about the 1999 forms than the 2017 forms. Ask it about a 2017 contract and it may answer with the 1999 numbers and clause references, with the same confidence.

In Bayan Clause Intelligence, the FIDIC track reads your contract, General and Particular Conditions together, so the notice periods it shows are the ones in your contract, and it flags every amendment to Clause 20 and its effect.

The Bayan Brief

The month's key legal updates and what's new in Bayan, once a month

Ask Bayan your first question

Or book a team demo and bring a real contract: 30 minutes is enough to know whether Bayan fits your practice

Book a Team Demo